Studies of needs, rationalization of devices, new installations, repairs and rehabilitations...
Installation of pathways and connection of 65,000 m of cables (approximately 1,900 cable heads)
Supply and installation of technical floors
Installation and connection of cabinets and equipment in MV and LV electrical rooms
Study, supply and installation of a 33KV MV line
Study, supply and installation of:
- Transformer room
- Strong current electricity
- Electrical cabinets
- Automation & Remote management
Average duration of construction sites between 5 and 8 months
MV substation
Supply and installation of technical floors
Assembly of the 2 automated control rooms
Installation of all electrical equipment, cabinets
Pulling and connection of 30,000m of cables
Replacement of the electrical cabinet
Replacement of DC motors with SIEMENS geared motors and drives (SINAMICS)
Replacement of relays by a SIMATIC S7-300 PLC networked with SINAMICS drives by ProfiBus
Supervision with a SIEMENS KTP 1200 display
Convenience networked with the PLC and drives via ProfiBus for
visualization and control of the different entities of the machine in
their different states
Process control cabinet for the SOCIM cement plant
Cabinets in 8MF: high degree of protection against sea salt - sheet metal and special paints (image 1)
Onshore Petroleum Products Storage Depot in the Port of Monrovia
TGBT
Process control cabinets
Lightings
Routing, pulling and connection of all cables
High current (MV and LV) and low current
Factory 20,000 m2 covered
Study, sizing of fluid and electrical channels
High current & low current realization
Wiring, installation and connection of 40 cabinets and boxes, 2 TGBTs
Study, supply and production of:
- Cabinets
- Automation
- Oversight
- Trials
- Commissioning
Electrical study and realization / pumping / hydrocarbons
Strong current
Low current
Instrumentation
Optical fiber
Replacement of 8DJH SIEMENS medium voltage cubicles
Supply, installation and commissioning
Supply, installation and commissioning of medium voltage cubicles in 8DJH SIEMENS
Wiring, installation and connection of 2500 KVA inverter cabinets
Connection of generating sets
BARTH cabinet wiring, PLC programming, IT, connection and commissioning.
SILO NIBS cabinet wiring, PLC programming, IT, connection and commissioning
Passage and connection of cables for the GRINDING 4 line box and commissioning.
400 / 220V cabinet cabling, fire detection, rack cabling and IT network, installation and commissioning Inverter, lighting installation and platform equipment LOGISTICS OFFICE
COLD UNIT cabinet wiring, PLC programming, HMI, IT, connection and commissioning.
Cabinet Cabling HR Offices
Electrical Installation Lighting and Automatic Doors of the Loading Dock
Electrical study and realization / pumping / hydrocarbons
Strong current
Low current
Instrumentation
Optical fiber